Cost of Delay: 14 Critical success factors for building an economic model (part 10)

Eric Graves- 03/9/17 06:30 PM

This is Part 10 in a 10-part series of posts discussing Cost of Delay and making objective decisions in new product development, based on economic analysis.

In this part, we discuss some critical success factors for implementing Project Economic Modeling and Economic Decision Making.

In this part, we discuss some critical success factors for successfully Implementing Project Economic Modeling and Economic Decision Making.

Requirements for an economic model in new product development

There are critical success factors -- requirements essentially -- required for ensuring the successful implementation of an economic model for new product development project decisions. As with all requirements, each has a varied level of importance and difficulty to implement. As such, we discuss the importance of each one in Must (M), Should (S), Could (C) terms and provide a short rationale for each requirement. We start with the easier to implement requirements, and move to the more difficult ones. (Note: in order to keep the list concise we left off the ‘Coulds’.)

You can view the complete guide to cost of delay here.

View My Guide to Cost of Delay

Easy and low risk success factors

1) (M) Build a Project Economic Model (PEM) spreadsheet.

Use the sales forecasts which the project approval was based on. If you don’t want to start from scratch, contact us and we’ll give you one of our templates. (Free!)

Why? People understand and buy into the results better when they can see them proven using some simple math in a spreadsheet.

2) (S) Plot monthly sales forecasts (as opposed to annual).

If only annual forecasts are available, estimate the monthly forecasts and plot them. For increased confidence, gather historical monthly sales for similar product launches in the past and try to emulate the shape of the curve.


b10p1p3fig1

Figure 1: Monthly Sales Forecast Plots Showing COD

Why? The results are more believable if they are visual. Plots of monthly sales show the impact of a one-month delay more clearly than plots of annual sales.

3) (S) Involve Sales, Marketing, and Finance in the COD calculation and reasoning.

Discuss the monthly sales forecast graph with sales, marketing, and finance. Specifically cover what happens if the product is released late. Does the sales incline get a steeper slope somehow? Is there a reduced peak? Does the sales decline move later if the product is launched later? Use one month, three month and six month delays as examples. Draw the projected curves using a markup tool on the original graph.

Why? Buy in to the COD calculation and economic decision making is much better if sales, marketing, and finance agree with the assessment.

4) (S) Estimate the per-month COD using a brute force method.

Replicate the delay curves you drew in #3 within your spreadsheet, and compare the cumulative profit in each case. This is done by shifting any increasing monthly forecasts to the right by the amount of the delay. If there will be a peak reduction, reduce all monthly profits by that same percentage. Add total profit for each delay. The difference between the profit in the delay case and the profit in the baseline is the COD for each delay.

b10p2b10p3
Figure 2: Monthly Sales Forecast Plots Showing 1 mo, 3 mo and 6 mo COD

Why? This ‘brute-force’ graphical method helps many people understand and buy into the COD value.

5) (M) Exclude project expenses in your Cost of Delay calculation.

When calculating the one-month Cost of Delay sensitivity, do not include labor or other expenses which may be incurred during a month of additional development time. Instead, consider the expense impact of each decision or delay separately.

Why? There are several reasons for this:

a. Expenses for any given decision vary a lot, and can include labor, lab costs, prototype parts, and many other types of costs. Any given decision which costs us a month could cost a lot or a little in project expenses.

b. If you keep expenses separated out, you can more easily determine the ROI associated with each decision. Expenses are the denominator of ROI.

c. In order to make cross-project decisions using COD, it is best if the COD itself isn’t already a function of how many people are on the project. For example, when prioritizing projects you often create pure delays but not R&D overspends. Keep COD a reflection purely of the opportunity value of the project and how that value degrades over time. Add the cost in separately where it’s needed.

d. The expense cost of one month of development is typically much less than the opportunity cost of a one month delay to market. Adding a month of expenses to COD doesn’t change your decisions much, but it does complicate them.

6) (M) Keep the model simple.

Don’t put in any ‘time value of money’ (e.g., NPV, IRR etc), or anything which makes it difficult for people to understand and use the model. Simple modifications are ok, like subtracting Marketing and/or General and Administrative (G&A) expenses from revenue.

Why? If the model isn’t easy to understand, it won’t be used and the benefits won’t be realized. NPV doesn’t substantially change the results anyway, especially in Lean development organizations where development times and product lifecycles are shorter.

7) (M) Establish a common Value Horizon for all projects.

Whether you use the entire lifecycle of each product or a fixed number of years, set a practice and use it for all projects. We find ‘cumulative profit after “X” years’ works well for comparing many different types of projects. (see Figure 2) Settling on the best Value Horizon seems like it could be difficult, but most companies do it easily. Usually the value horizon we use is 3, 4 or 5 years, and we set it once with a little discussion and keep using it.

Why? This allows better tradeoffs between projects, as they are more apple-apples comparisons.

8) (M) Help people understand that inaccurate sales forecasts do invalidate the model.

Help everyone recognize that, while the model is built around estimated sales volume forecasts, and they are often inaccurate, most outputs of the economic model are directly proportional to sales volume. The relative importance of delay vs. sales volumes vs. unit costs stays the same even if volume changes. For more information see the post on this topic.

Why? One of the largest objections and impediments to economic modeling is from the lack of certainty in the base inputs – the sales forecasts. Eliminating this objection is critical to buy-in across the organization.

Sensitivity to sales

Figure 4: Impact of Error in Sales Forecasts

More difficult success factors

9) (S) Economically model every project, of every type, to determine its Cost of Delay.

Whether they are new products, cost reductions on existing products, process improvements, CAPAs, or any other type of initiative, develop an economic model. Even products which lose money and seemingly have a negative COD, but which open doors to new markets and future profits, can have a quantified COD which includes the delay of value behind those doors. Different types of projects have different economic models, requiring different input-estimates, but they all have a COD that can be estimated.

Why? COD is the Golden Key (as Don Reinertsen puts it). It enables objective priority and resourcing decisions across all types of projects, and is critical in establishing optimal WIP constraints – i.e., when to start another project and when to wait.

10) (M) Promote the use of the economic model.

Management should publically recognize that we will be correct more often by using economic analysis with some estimates in it, rather than making decisions based entirely on gut-feel. The more profitable choice is unintuitive often enough that it pays to analyze our decisions economically. Management and team members should regularly ask, “What does the economic analysis say?” Publish results frequently, and note how economic analysis helped the team come to a better decision, faster.

Why? Economic Analysis takes a little time and effort. Gut-feel decisions are habit, and they are often easier than analytical decisions, just not as correct and profitable. Some people will need to be reminded of the benefits, or they won’t continue to make the effort. If we don’t use it, we lose it.

An analogy I like to use here is estimating the distance to the pin while golfing. Do you look for the distance markers that are there, or do you just ‘eyeball it’? Looking at the markers is doing a simple analysis. By looking at the markers and eyeballing it together your eyeball estimates will get better. However, you will still be better off doing a quick analysis whenever you can.

11) (S) Establish a Minimum Decision ROI for project decisions.

For any given decision, how much return do we need before deciding to do it? The Minimum Decision ROI is a function of the projects we have waiting for funding, and the opportunities available within other active projects. We recommend setting a baseline Minimum Decision ROI and use it across all projects. Review and update it quarterly.

Why? With each decision, we should profit as much or more from that decision than we could by putting our expense money toward something else.

12) (S) Establish Minimum Expected Value, spending limits, and other safety factor(s) for decisions.

See the previous post for more on these.

Why? To allow the safer decisions to move forward more quickly, for an even higher profit gain.

13) (S) Create accurate plans and have a detailed understanding of true resource availability.

Have good, detailed, up-to-date project plans, a good understanding of which resource(s) and work is Critical Chain, and what people’s true availability is.

Why? These allow you to have a better estimate for the impact a change will have on the launch date. With better delay estimates, our analyses are more accurate, and we achieve more buy-in and higher profit. This one is in the ‘not so easy’ section because it is difficult - unless you have a tool (PLAYBOOK) that makes accurate planning easy.

14) (S) Get direct customer feedback.

For decisions that impact sales volume or price, turn to your customers for representative feedback. Get better feedback about what your customers truly value by using Lean Startup methods. Also, remember that we don’t need to know exactly what ‘% change in volume’ will result from a particular change to the product. We can, instead, determine the break-even value and move forward if we expect to be above that value.

Why? Even the people in our organization who are experts on our customers (Chief Engineer, Marketing, Sales, etc.), will overvalue some ideas and undervalue others. We are better off learning what customers actually need and will pay for.

Summary and series wrap-up

In summary, the success of project economic modeling requires buy-in and a commitment from the organization to base new product development decisions in part on economics. Although it takes a little practice, discipline and work up front, once the model is in place, the level of effort is small compared to the payback!

I will conclude this series by adding one more key benefit to understanding Cost of Delay and economic analysis. COD is the key to resolving one of the primary root causes of the slow and overloaded conditions of traditional product development.

Many problems stem from too much visibility to project and company expenses, and a lack of visibility to COD. A focus on expenses causes local optima within departments, rather than optimizing the entire system. It pushes us toward larger batches and higher capacity utilization, which in turn cause big delays, lower quality products, frustrated and stressed-out people, and reduced profits.

Cost of Delay is the magic compass that helps counteract the natural forces pushing us into these stable and slow traditional conditions. With COD showing us the way, we see the value of spare capacity, limited WIP, better risk management, and smaller batches, all of which are critical to becoming a truly Lean organization.

Please let us know if you have any questions, comments, or requests for future topics.

You can download the complete guide to cost of delay here.

Download my eBook

  • Part 1, How can the Cost of Delay improve product development velocity and increase profits?

  • In Part 2, What is the definition of Cost of Delay?

  • Part 3: How to quickly estimate the Cost of Delay.

  • Part 4: How to quickly estimate the other terms generally required to create a project economic model.

  • Part 5: Examples of how to calculate the cost of delay and the subsequent ROI of making some common project trade-offs.

  • Part 6: Important factors to consider when implementing a project economic model and how to manage uncertainty of model inputs. 

  • Part 7: How to calculate the economic value of a decision quantitatively.

  • Part 8: How to communicate and account for uncertainty in each decision's impact on launch date, sales volume, and the other Economic Variables.

  • Part 9: How to increase certainty in our economic decisions, in part by increasing the accuracy of our impact estimates.

  • Part 10: Critical success factors for Implementing Project Economic Modeling and Economic Decision Making.

Related Posts: 

WSJF and How to Calculate It

WSJF and Architectural Runway

Don Reinertsen on cost of delay

Wikipedia on cost of delay