There are three new reports available: Status History, Project Status Trends, and Impact Reasons List.
Status History
The Status History report shows one or more projects and each row is a Major Milestone. The colors indicate the status of the milestone on its buffer chart by week. The numbers below the colored row indicate the number of days of change (+/-X) for that week.
Project Status Trends
The Project Status Trend report shows one or more projects and each vertical slice is a Major Milestone. The colors indicate the status of the milestone on its buffer chart that week giving you a portfolio view of all Major Milestones and their buffer status by week.
Impact Reasons List
The Impact Reasons List shows one or more projects and a list of all documented impact reasons for each Major Milestone. The reporting date and the buffer impact (in days and percent) are also shown.